Project

4 TPH/12 bar(g) STEAM BOILER SYSTEM PACKAGE

Client

Elastomeric Engineering Company Ltd

Installation of 4 TPH/12 bar(g) bio-mass steam Boiler plant at Elastomeric Engineering Company Ltd at Horana. Steam Boiler supplier – Industrial Boilers ltd, India.

Dates Employed

Oct 2014 – Dec 2014

Employment Duration

3 Months

Project Value

USD 110,000 + LKR 16 Mn

4 TPH/12 bar(g) bio-mass steam Boiler

Type of Boiler
Combination type, Water tube and smoke tube boiler
Solid fuel
Saw dust and rubber wood logs
Feeding method
Semi -Auto (70% auto and 30% manual)
Mode of combustion
Balance draft (Mechanical draft)
Air pollution control system
Includes Bag Filter
Heat Recovery unit
APH (Air pre-heater)
Start Erection work
Oct 2014
Scheduled Date of commissioning
27 December 2014
Want to know more ?

Please fill the below details and send us.

    To make requests for further information, contact us

    Make a Call
    +94 11 268 0095
    E mail us
    [email protected]
    For Calibration Services
    [email protected]